Misreading "8 days" as a full stop
Misreading the 8-day holiday as a full stop: the real shutdown is longer.
The misreading
The official Spring Festival block is about 8 days. The factory shutdown is one to three weeks. The gap between the two numbers is where inventory plans die: buyers assume the official block is the production pause, and it is not.
The three calendars
| Layer | Length |
|---|---|
| Official holiday | ~8 days |
| Factory shutdown | 1–3 weeks |
| Full logistics recovery | 3–4 weeks |
The fix
Plan production against the factory shutdown calendar, not the public holiday calendar. The official block tells you when offices close; the shutdown calendar tells you when goods stop moving.
The rule
For manufacturing, every date extends. Buffer 2–3 weeks past whatever the official calendar says.